2024

Construction of the Coking and Power Plant in the Altanshireet Industrial Park has started with the capacity to produce 1.0-1.5 million tonnes of coke.

2023

  • First blasting works at the mines for production purposes
  • Trial period of the Coal Washing Plant within the Altanshireet Industrial Park Project with a capacity of producing 1.5 million tons of washed coal annually.
  • The Government of Mongolia issued the permit for the operation of the Altanshireet Industrial Park with Resolution No. 257 dated 5 July 2023
  • The project to build a loading/unloading terminal at Tavan Tolgoi station in Tsogtsetsii sub-province of Umnugobi Province started
  • Completion of the Worker’s Facility and Canteen for the workers at Khangi and Nomgon crossings within the Zuunbayan-Khangi railway line
  • Completion of Mandakh-Naran 5 Complex for up to 288 residential households in Dornogobi Province
  • “Khugjil-2” Worker’s Facility was completed in Khandgait mines in Eruu sub-province of Selenge Province
  • Infinity Space LLC’s Worker’s Facility and Canteen was constructed in Eruu sub-province of Selenge Province

2022

  • MONEM Explosive Emulsion Factory
  • Completion of the Zuunbayan-Khangi railway line of 226.9km under the Concession Agreement for the BOOT Build-Own-Operate-Transfer
  • Completion of the Khangi, Nomgon crossing within the framework of the Zuunbayan-Khangi railway lin

2021

Completion of the Iron ore wet processing plant within the Altanshireet Industrial Park Project with a capacity to wash 1-1.5 million tonnes of ore and produce iron ore concentrate.

2020

Completion of the worker’s office and apartments for the Altanshireet Industrial Park Project

2019

  • Completion of 7 block of living quarters for mining workers, Canteen with 300 people capacity, Sports and Arts Centre, Hotel, 2 Electricity Substations and ‘Khugjil-1’ Complex.
  • Wagon depot capable of repairing 2,100 wagons annually.
  • Altanshireet Industrial Park Project planning work in Altanshiree sub-province of Dornogobi Province.
  • 3 loading and unloading terminals with 10.4 km of main roads and 18 km of railways within the framework of the Altanshireet Industrial Park Project
  • Completion of Mandakh Naran Complex-3 and Mandakh Naran Complex-4 for up to 288 residential households.

2018

  • Completion of Mandakh Naran 2 Complex for 284 residents in Zamiin-Uud sub-province of Dornogobi Province
  • Completion of Sports Complex with up to 500 people capacity in Zamiin-Uud sub-province of Dornogobi Province
  • Completion of construction for residential apartment for 48 families and a 100-bed kindergarten in Dornogobi Province

2017

  • First railway export of coal from Olon-Ovoo station in Dornogobi Province to Erlian in the People’s Republic of China
  • Completion of the Development Centre for people with disabilities, senior citizens and women for 272 individuals in Mandakh Naran I Complex of Dornogobi Province

2015

  • 50-70 MW Substation with a capacity of 110kW was constructed
  • Completion of Hospital with 50 bed in Dornogobi Province
  • Completion of Kindergarten for 150 children in Zamiin-Uud sub-province of Dornogobi Province

2014

  • Iron ore dry processing plant production capacity was upgraded to 400 tonnes per hour
  • US TREAD Corporation’s Open-Emulsion Explosives plant was introduced to the blasting production to raise the quality standards for mine blasting operations

2011

Khandgait Customs Control Zone was constructed in Eruu sub-province of Selenge Province

2010

15 Locomotives and 3,003 Wagons were introduced to the railway line for transportation and logistics

2009

115 kilometer of railway spur was constructed in Eruu sub-province of Selenge Province

2007

Iron ore dry processing plant using dry magnetic method with a production capacity of 150 tonnes per hour.

2005

First blasting works at the mines for production purposes

2004

Iron ore mining operations started in Eruu sub-province of Selenge Province