2024
Construction of the Coking and Power Plant in the Altanshireet Industrial Park has started with the capacity to produce 1.0-1.5 million tonnes of coke.
2023
- First blasting works at the mines for production purposes
- Trial period of the Coal Washing Plant within the Altanshireet Industrial Park Project with a capacity of producing 1.5 million tons of washed coal annually.
- The Government of Mongolia issued the permit for the operation of the Altanshireet Industrial Park with Resolution No. 257 dated 5 July 2023
- The project to build a loading/unloading terminal at Tavan Tolgoi station in Tsogtsetsii sub-province of Umnugobi Province started
- Completion of the Worker’s Facility and Canteen for the workers at Khangi and Nomgon crossings within the Zuunbayan-Khangi railway line
- Completion of Mandakh-Naran 5 Complex for up to 288 residential households in Dornogobi Province
- “Khugjil-2” Worker’s Facility was completed in Khandgait mines in Eruu sub-province of Selenge Province
- Infinity Space LLC’s Worker’s Facility and Canteen was constructed in Eruu sub-province of Selenge Province
2022
- MONEM Explosive Emulsion Factory
- Completion of the Zuunbayan-Khangi railway line of 226.9km under the Concession Agreement for the BOOT Build-Own-Operate-Transfer
- Completion of the Khangi, Nomgon crossing within the framework of the Zuunbayan-Khangi railway lin
2021
Completion of the Iron ore wet processing plant within the Altanshireet Industrial Park Project with a capacity to wash 1-1.5 million tonnes of ore and produce iron ore concentrate.
2020
Completion of the worker’s office and apartments for the Altanshireet Industrial Park Project
2019
- Completion of 7 block of living quarters for mining workers, Canteen with 300 people capacity, Sports and Arts Centre, Hotel, 2 Electricity Substations and ‘Khugjil-1’ Complex.
- Wagon depot capable of repairing 2,100 wagons annually.
- Altanshireet Industrial Park Project planning work in Altanshiree sub-province of Dornogobi Province.
- 3 loading and unloading terminals with 10.4 km of main roads and 18 km of railways within the framework of the Altanshireet Industrial Park Project
- Completion of Mandakh Naran Complex-3 and Mandakh Naran Complex-4 for up to 288 residential households.
2018
- Completion of Mandakh Naran 2 Complex for 284 residents in Zamiin-Uud sub-province of Dornogobi Province
- Completion of Sports Complex with up to 500 people capacity in Zamiin-Uud sub-province of Dornogobi Province
- Completion of construction for residential apartment for 48 families and a 100-bed kindergarten in Dornogobi Province
2017
- First railway export of coal from Olon-Ovoo station in Dornogobi Province to Erlian in the People’s Republic of China
- Completion of the Development Centre for people with disabilities, senior citizens and women for 272 individuals in Mandakh Naran I Complex of Dornogobi Province
2015
- 50-70 MW Substation with a capacity of 110kW was constructed
- Completion of Hospital with 50 bed in Dornogobi Province
- Completion of Kindergarten for 150 children in Zamiin-Uud sub-province of Dornogobi Province
2014
- Iron ore dry processing plant production capacity was upgraded to 400 tonnes per hour
- US TREAD Corporation’s Open-Emulsion Explosives plant was introduced to the blasting production to raise the quality standards for mine blasting operations